Commercial, Batumi
Batumi Coast Hotel
- Employer
- Hotel investor
- Area
- 28,600 m²
- Floors
- 22
- Duration
- 26 months
- Planned handover
- 01.06.2025
- Actual handover
- 27.05.2025
5 days early
A 260-room hotel, handed over five days before the season opened.
The hotel holds 260 rooms, a conference hall and a rooftop restaurant over 22 floors. The handover date was tied to the opening of the summer season.
Room bathrooms were built as prefabricated pods in the factory and placed floor by floor. That decision cut four weeks from the finishes.


Next projectRiyadh Vocational Training Campus