Delivery record
Every project we have handed over since 1986, late ones included.
| Project | Country | Planned | Actual | Deviation |
|---|---|---|---|---|
| Kartaltepe State Hospital | Türkiye | 14.03.2026 | 12.03.2026 | −2 days |
| Baku Harbour Office Campus | Azerbaijan | 30.11.2025 | 30.11.2025 | 0 days |
| Almaty North Residences | Kazakhstan | 15.09.2025 | 24.09.2025 | +9 days |
| Batumi Coast Hotel | Georgia | 01.06.2025 | 27.05.2025 | −5 days |
| Riyadh Vocational Training Campus | Saudi Arabia | 20.02.2025 | 18.02.2025 | −2 days |
| Levent North Office Tower | Türkiye | 30.09.2024 | 30.09.2024 | 0 days |
| Manisa School Campus | Türkiye | 30.04.2024 | 27.04.2024 | −3 days |
| Medina Public Service Building | Saudi Arabia | 04.03.2024 | 03.03.2024 | −1 day |
| Sakarya Health Campus | Türkiye | 09.01.2024 | 31.12.2023 | −9 days |
| Tekirdağ Shopping Centre | Türkiye | 26.12.2023 | 18.12.2023 | −8 days |
| Maslak Cultural Centre | Türkiye | 26.11.2023 | 15.11.2023 | −11 days |
| Manisa Hotel | Türkiye | 24.07.2023 | 13.07.2023 | −11 days |
| Söğütözü Public Service Building | Türkiye | 15.06.2023 | 11.06.2023 | −4 days |
| Bursa Residences | Türkiye | 03.01.2023 | 30.12.2022 | −4 days |
| Bucharest Cultural Centre | Romania | 01.10.2022 | 01.10.2022 | 0 days |
| Sivas Hotel | Türkiye | 15.08.2022 | 15.08.2022 | 0 days |
| Sakarya Production Plant | Türkiye | 17.07.2022 | 16.07.2022 | −1 day |
| Etimesgut Training and Research Hospital | Türkiye | 13.05.2022 | 06.05.2022 | −7 days |
| Kutaisi Health Campus | Georgia | 07.11.2021 | 31.10.2021 | −7 days |
| Maslak Courthouse | Türkiye | 08.08.2021 | 29.07.2021 | −10 days |
| Gebze Office Building | Türkiye | 22.06.2021 | 20.06.2021 | −2 days |
| Eskişehir State Hospital | Türkiye | 03.01.2021 | 01.01.2021 | −2 days |
| Erzurum Courthouse | Türkiye | 14.11.2020 | 07.11.2020 | −7 days |
| Trabzon Metro Station | Türkiye | 15.07.2020 | 12.08.2020 | +28 days |
| Almaty Residences | Kazakhstan | 21.06.2020 | 17.06.2020 | −4 days |
How we count
The planned date is the handover date in the signed contract, updated only by approved change orders. The actual date is the date of the provisional acceptance certificate. Deviation is the number of calendar days between the two.