Commercial, Ankara
Mavi Kule Office Building
- Employer
- Private investor
- Area
- 38,400 m²
- Floors
- 24
- Duration
- 30 months
- Planned handover
- 30.06.2027
- Current forecast
- 21.06.2027
9 days early
A 24-storey office building; the current forecast is nine days early.
The building will provide 38,400 m² of offices on 24 floors. The structure was completed in September 2026.
The facade is ahead of plan and mechanical works are four points behind. The team moves to a second shift in November; the gap is expected to close in January.
Milestones
- 10.03.2025Excavation completedDone
- 18.09.2026Structure completedDone
- 29.01.2027Building envelope closedPlanned
- 30.06.2027Provisional acceptancePlanned

Site report
Mavi Kule Office Building
Ankara, 38,400 m², 24 floors
- Planned handover
- 30.06.2027
- Current forecast
- 21.06.2027
- Difference
- 9 days early
- StructureActual %100 / Planned %100
- FacadeActual %62 / Planned %58
- MechanicalActual %41 / Planned %45
- ElectricalActual %40 / Planned %39
- FinishesActual %22 / Planned %20
- LandscapingActual %6 / Planned %5