Industrial, Jeddah
Jeddah Logistics Centre
- Employer
- Logistics operator
- Area
- 124,000 m²
- Floors
- 2
- Duration
- 22 months
- Planned handover
- 20.12.2026
- Current forecast
- 14.12.2026
6 days early
A 124,000 m² logistics centre; the current forecast is six days early.
The centre combines a warehouse with 96 loading docks and a cold-chain section. The steel roof trusses were fabricated in our workshop in Türkiye, not on site.
The project is in its final stretch: structure and facade are complete, landscaping and commissioning continue.
Milestones
- 17.02.2025Site handed overDone
- 30.09.2026Facade completedDone
- 20.12.2026Provisional acceptancePlanned

Site report
Jeddah Logistics Centre
Jeddah, 124,000 m², 2 floors
- Planned handover
- 20.12.2026
- Current forecast
- 14.12.2026
- Difference
- 6 days early
- StructureActual %100 / Planned %100
- FacadeActual %100 / Planned %100
- MechanicalActual %91 / Planned %90
- ElectricalActual %89 / Planned %88
- FinishesActual %78 / Planned %76
- LandscapingActual %55 / Planned %52